North High School
In This Section

North High School

North High School

North High School is scheduled to undergo a renovation and expansion as outlined below. To received periodic updates on project milestones and other news please sign up to receive e-alerts

School Location: 1500 James Ave N. Minneapolis, MN. 55411

Scope of Work

  • Replace the public address, fire alarm, and clocks systems completely
  • Replace flooring in limited areas of the building

Project Updates: 

August 16, 2019: Project is tracking on schedule. Generators, exterior lighting replacement and courtyard improvements are currenlty being worked on. 

July 16, 2019: New generators and exterior lighting are being worked on and are on track to be completed by the start of school. 

April 17, 2019: On April 16, 2019 the Board of Education approved the contract for proceeding with North's construction project. Construction is set to start the first week of May in areas that are not being used for construction, with an anticipated completion date of August, 2019. Construction Results Corporation will be the contractor for this project.

March 4, 2019:  This work is currently out for public bid and final scope will be determined by the end of March. Items that are being bid for Summer 2019 work include full Public Address system replacement, fire alarm system replacement, clock replacement, limited flooring replacement, and several options for courtyard security and enclosure. 

November 21, 2018:  Team is still in design phase.

October 10, 2018: Currently in design phase of project. Will provide more information and updates as project progresses to next phase.

Project Schedule (subject to change):

Design Contract Approval

Design: Spring 2018

Pre-Construction: Summer / Fall 2018

Construction:  Winter 2018- Summer 2019

General Contractor: Construction Results Corporation

Completion: Fall 2019