Jenny Lind Entrance and Lighting Project

Jenny Lind Entrance and Lighting Project
Rendering of New Entrance

 

Jenny Lind Elementary School is scheduled to undergo a renovation and is outlined below.  To receive periodic updates on project milestones and other news please sign up to receive e-alerts.

School Location: 5025 Bryant Ave N, Minneapolis MN. 55430

Scope of Work:

Jenny Lind Elementary school is scheduled to be renovated to accommodate a new safe & welcoming visitor entrance, new monument sign, office upgrades and lighting upgrades.

Project Updates: 

June 24, 2020: Construction has begun. Lighting replacement is happening on the first floor and demolition of the office has started.  

April 12, 2021: Sheehy Construction was the low bid and are awaiting BOE approval on April 13, 2021. 

February 24, 2021: Construction documents are now available. 

Project Schedule (subject to change):

Design: Fall/Winter 2020
Bid Opening: Friday, March 19, 2021 at 10:00am
MPS Board Approval: Tuesday, April 13 2021
Construction Start: June 2021
Substantial Completion: August 2021

General Contractor: Sheehy Construction Company