Green Central – Full-Service Community School

Green Central – Full-Service Community School


Green Central Elementary is scheduled to undergo a renovation and is outlined below. To receive periodic updates on project milestones and other news please sign up to receive e-alerts.

School Location: 3416 4th Ave South, Minneapolis MN. 55408

Scope of Work:

Green Central – Full-Service Community School

The work at Green Central includes the development of a full-service community school space in the current music and band rooms.  The music and band rooms will be relocated to the unused locker rooms on the second floor.

Project Updates:

September 8, 2021: The project has been contracted. Demolition is expected to begin 9/20/2021. 

July 6, 2021: The project has been solicited for bids. Bids are due July 15, 2021.  

June 4, 2021: Design is ongoing and expected to be complete in mid-June.  Bid documents will be solicited June 22, 2021.  

May 4, 2021: Design is ongoing and expected to be complete in early June.

April 6, 2021: The design is in progress.  We are hoping to set up user group meetings to review the design in a couple of weeks.

Project Schedule (subject to change):

Design: Spring 2021

Construction: Summer 2021

Completion: Fall 2021

General Contractor: TBD