Franklin Middle School STEAM Magnet is scheduled to undergo a renovation and is outlined below.  To receive periodic updates on project milestones and other news please sign up to receive e-alerts.

School Location: 1501 Aldrich Ave. N, Minneapolis MN. 55411

Scope of Work:

Franklin Middle School – Robotics Space

The work at Franklin includes the development of a robotics space in room A100. 

Project Updates:

September 8, 2021: Construction is complete.

July 6, 2021: Construction is on schedule. Demolition, wall patching, and painting is complete. Flooring is being installed this week. Lighting, ceilings, and doors/hardware are scheduled for next week.  

June 4, 2021: Sheehy Construction Company has been contracted for the work.  On-site work is scheduled to begin June 14, 2021.

May 4, 2021: We are currently contracting the project.  On-site work is scheduled to being June 14, 2021.

April 6, 2021: The construction documents have been sent to several contractors for bid quotes.  Bids are due April 16, 2021.

Project Schedule (subject to change):

Design: Spring 2021

Bid Due: April 16, 2021

Construction: July 16, 2021

Completion: September 14, 2021

General Contractor: TBD