District Wide Site Improvements
In This Section

District Wide Site Improvements

District Wide Site Improvements

District Wide Site Improvements 

District Wide Paving projects at multiple schools including parking lots, drives, sidewalks, hard play surfaces, and other paved surfaces.  

Scope of Work 

The project scope is to repair and/or replace concrete sidewalks and asphalt parking lots, including chip sealing, at the following school sites:

1. Anwatin (bus lane only)

2. Bethune (sidewalks along Emerson only)

3. Patrick Henry H.S. (parking lot crack filling and chip sealing )

4. Justice Page M.S. (parking lot crack filling and chip sealing)

5. Loring Elementary (parking lot reclamation, 2 new aprons, concrete sidewalks, seal coat playground area)

6. North  H.S. Field (seal coat under bleachers only)

7. Transportation Services (chip seal North & East employees parking lots, concrete replacement on North side- no work in bus area)

8. Washburn H.S. (parking lot crack filling & chip sealing)

9. Wilder Complex (parking lot crack filling & chip sealing- Chicago large lot, small staff lot, & East bus lane)

10. Davis Center (raise 5 manhole covers, asphalt repair, crack filling, chip sealing)

11. Edison (concrete sidewalks, curb cuts, manhole cover)

Project Updates:

June 30, 2020:

  1. Anwatin: Bus lane is complete. 
  2. Bethune:  Sidewalks along Emerson Avenue are complete. 
  3. Davis Center: North Parking Lot will be closed June 29th-30th for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.
  4. Edison: Sidewalks & curb replacements are complete. 
  5. Henry:  Sidewalk replacement is complete.  Parking lots will be closed June 29th – July 1st for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.
  6. Justice Page:  Parking lots will be closed June 29th – July 1st for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.
  7. Loring: North Parking Lot has been removed and will be re-paved.  Work scheduled to be complete July 3, 2020 (weather dependent).
  8. North Field:  Area under bleachers being crackfilled and seal coated week of June 22, 2020.
  9. Transportation Center: Replacement of concrete sidewalks is complete.  Parking lot areas outside of fence line will be closed June 29th – July 1st for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.
  10. Washburn H.S.:  Both parking lots will be closed June 29th – July 1st for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.
  11. Wilder Complex:  All parking lots and bus lane by Door #16 will be closed June 29th – July 1st for Chip Sealing, then July 13th-15th for sweeping, fogsealing, and striping.

April 16, 2019: Construction begins summer 2020

Project Schedule ( subject to change):

Design phase: complete

Plans Available: March 13, 2020

Formal Bid Opening: April 3, 2020

MPS Board Approval Meeting:  April 14, 2020

Construction begins: June 6, 2020

Substantial competition: August 20, 2020

Final Completion: December 2020

 