Building Automation Upgrade 2019
In This Section

Building Automation Upgrades

Building Automation Upgrades

Building Automation Upgrades Overview 

We are upgrading the Building Automation System to provide better control for the heating and air conditioning. 

Locations: 

  • Barton
  • Northeast
  • Olson
  • Paige
  • Sullivan 
  • Washburn

Scope of Work

This project will be updating new controls, new hardware, software, and data gathering equipment. 

KFI is the consultant working on this project. 

Project Updates:

April 12, 2019: Project is in preliminary stage 

Project Schedule (subject to change):

Preliminary design- May/June 2019

Bids- August 2019

Installation- October 2019

Project completion- March 2020