The FAIR School is scheduled to undergo construction as outlined below. To receive periodic updates on project milestones and other news, please sign up to receive e-alerts.

School Location: 10 South 10th St. Minneapolis, MN. 55403

Scope of Work:

The project scope is to provide a safe and welcoming entrance. 

1. Provide RFID readers and releases to main entrance doors

2. Add fortification of large glass panels at the main entrance and potentially auxiliary entrance doors using films. 

3. Upgrade the school wide public address system.

4. Add door alarms to exterior doors.

5. Upgrade entrance to create better security at entrance with storefront 

Project Updates: 

January 19, 2021: Work is complete. 

November 16, 2020: We are excited to announce that The FAIR School Student Safety project is almost complete. 

The main entrance vestibule, main office area, and lobby areas were updated with the goal to provide a safe and welcoming entrance.

Work included new card reader system for security access, fortification of large glass panels at the main entrance and potentially auxiliary entrance door  using 3M film, upgrading the school wide public address system, adding door alarms to exterior doors.

New office furniture is on the way.  Unfortunately, COVID has caused delays on custom fabricated items.  We hope to have all furniture in place by early November.

Project Schedule (subject to change):

Design: Fall/Winter 2019

Bid Due: Wednesday,March 11, 2020 pm

MPS Board Approval: Tuesday, April 14th, 2020

Notice to Proceed: Friday, April 17, 2020 (Contingent on Board Approval)

Construction Commenced: June 6, 2020

Substantial Completion: August 14, 2020