Waite Park Community School is scheduled to undergo a renovation and expansion as outlined below. To received periodic updates on project milestones and other news please sign up to receive e-alerts.

School Location: 1800 34th Avenue NE Minneapolis, MN. 55418

Scope of Work:

  • Safe, secure and welcoming entrance
  • Food service/lunchrrom upgrades
  • Auditorium upgrades
  • All lighting (interior/exterior) will be converted to LED
  • Select electrical panel board replacement
  • Select electrical distribution panels & wire 
  • Replacement of the Public Address System (PA)
  • Replacement of clock system
  • Replace corridor 12" x 12" ceiling tile with ACT drop in ceiling tiles 
  • Replace carpeting in the Media Center 

Project Updates:

April 12, 2021: We are now on the second phase of this project. Work includes kitchen/lunchroom, auditorium, elevator, and electrical upgrades. 

August 12, 2020: Project is on track and set to be substantially complete on August 28th. 

February 10, 2020: Project will be completed in two phases over two summers. Phase 1 will be all main floor construction, including the new Safe and Secure Entrance. Phase 2 will be the Ground Floor construction and will include the Auditorium and Food Service/Lunchroom Upgrades.

Project Schedule (subject to change):

Design: Fall/Winter 2020

Pre-Construction: Mandatory Pre-Bid was held on January 17, 2020. Project Bid Opened on March 13, 2020. Board of Education approval on April 14, 2020. 

Construction: Summer 2020 and Summer 2021

General Contractor: Construction Results Corporation 

Designer: 292 Design Group/Hallberg Engineers

Substantial Completion: Phase 1 substantial completion will be August 2020 and Phase 2 substantial completion will be August 2021