Bethune Community School
In This Section

Bethune Community School

Bethune Community School

 

Bethune Community School is scheduled to undergo a renovation and expansion as outlined below. To received periodic updates on project milestones and other news please sign up to receive e-alerts.

School Location: 919 Emerson Avenue North, Minneapolis, MN. 55411 

Scope of Work:

  • Safe, secure and welcoming entrance
  • Food service/lunchroom upgrades
  • All lighting (interior/exterior) will be converted to LED
  • Replacement of trash enclosure
  • Refinishing and re-striping of the gym floor

Project Updates:

August 12, 2020: The exterior entrance slab, food service kitchen shell and undergorund work, and gym floor refinishing are complete. Substantial completetion will be around August 28th, 2020.

March 5, 2020: During Spring Break 2020 there will be abatement activities in the NW Storage area in and off of the Multi-Purpose room. They will set up containment to complete the work. 

February 7, 2020: Project Bid on January 24,2020 and MPS will execute a contract with Sheehy Construction Company. They are the General Contractor that was the lowest qualified bid on the February 11, 2020 Board of Education Meeting.  

Project Schedule (subject to change):

Design: Fall 2019

Pre-Construction Conference: Februay 24, 2020

Construction:  May 2020- August 2020

General Contractor: Sheehy Construction Company

Substantial Completion: August 2020